A logo
A logo
A logo
A logo
A logo

Case Study 3 – Employer

The Problem: The Employer on a multi-million refurbishment project was concerned with the significant delays occurring on site and the rapidly escalating cost of the project. He was also [...]

Case Study 3 – Employer2020-06-29T20:49:41+01:00

Case Study 2 – Main Contractor

The Problem: On a £2 million main contract, with delays resulting from numerous Variations, the Employer decided to terminate the main contract, even though the project was just 3 [...]

Case Study 2 – Main Contractor2020-06-29T12:32:14+01:00

Case Study 1 – Sub-Contractor

The Problem: The sub-contractor had completed his installations on site over a ten weeks period. He had issued three applications for payment, but another month had passed without receiving [...]

Case Study 1 – Sub-Contractor2020-06-29T12:31:53+01:00
Go to Top